WARNING: You're looking at a page from the old site. We have relaunched with live stimulus data. Learn more here.
Welcome to Stimulus Watch 2.0. While our original site featured proposed stimulus projects taken from the U.S. Conference of Mayors…
Jerry Brito talks about the new Stimulus Watch site on WUSA Channel 9 News.
Stimulus Watch was inspired in part by Washington Watch, a site that lets you find, rate, describe, and discuss legislation…
OpenRegs.com
Find government regulations by issue or agency. Comment, add links and subscribe to regulations.
Below are the "shovel-ready" projects for which this city submitted in the 2008 U.S. Conference of Mayors report. You can click on a project to read (and add to) its description. You can also discuss the project and vote on whether you believe it is critical or not.
The total cost of all the projects submitted by Northampton is $33,495,000
| Description | City | State | Jobs | Cost | Program Type | Vote Ratio |
|---|---|---|---|---|---|---|
| Pavement Management - 100 road miles | Northampton | MA | 30 | $15,000,000 | Streets/Roads | -6 |
| Manhan Rail Trail - 2.4 miles | Northampton | MA | 18 | $3,100,000 | Streets/Roads | 33 |
| Milton Street Repaving | Northampton | MA | 24 | $1,500,000 | Streets/Roads | -5 |
| Hinckley Street Repaving | Northampton | MA | 24 | $1,000,000 | Streets/Roads | 16 |
| Replace Cast Iron and Asbestos Cement Water Mains - 20 miles | Northampton | MA | 15 | $6,000,000 | Water | 16 |
| Repalcement of Sewer Mains | Northampton | MA | 10 | $4,000,000 | Water | 13 |
| Slip lining sewer mains | Northampton | MA | 5 | $1,000,000 | Water | 8 |
| Installation of Zinc Orthophosphate Chemical Feed at Water Treatment Plant | Northampton | MA | 8 | $700,000 | Water | 2 |
| Upgrade well chlorination equipment at two wells | Northampton | MA | 12 | $695,000 | Water | 11 |
| Flood Control - Dike, levee and pump station upgrades | Northampton | MA | 6 | $500,000 | Water | 11 |