| Resurfacing of approximately 10 miles of various industrial streets within the village. Our industrial streets are typical 2-lanes, 44 back to back of curb and gutter. It will be resurfaced with 1.5 inches of bituminous asphalt, some storm sewers, |
Addison |
IL |
60 |
$12,200,000 |
Streets/Roads |
-116 |
| Resurfacing of Swift Road from US 20 to Collins Avenue, an approximate 4 mile long village minor arterial raodway with a five lane cross section (the fifth lane dedicated as a planted median strip or left turn lane) that carries about 20,000 vehicles |
Addison |
IL |
60 |
$9,245,000 |
Streets/Roads |
-77 |
| Resurfacing of approximately 10 miles of various residential streets within the village. Our residential streets are typical 2-lanes, 34 back to back of curb and gutter. It will be resurfaced with 1.5 inches of bituminous asphalt, some storm sewers, |
Addison |
IL |
60 |
$4,400,000 |
Streets/Roads |
-56 |
| Provide water to the 53 Estetes subdivision by the installation of eight inches diameter watermains and stubs, valve vaults, fire hydrants, valve boxes, bituminous patching and restoration of disturbed areas such as parkways, driveways, ditches and draina |
Addison |
IL |
50 |
$4,400,000 |
Water |
-61 |
| Miscellaneous local street resurfacing |
Alsip |
IL |
150 |
$4,500,000 |
Streets/Roads |
-46 |
| Springfield and Hamlin Avenue Reconstructions |
Alsip |
IL |
23 |
$700,000 |
Streets/Roads |
-17 |
| 128th Place and Ridgeway Reconstruction |
Alsip |
IL |
22 |
$650,000 |
Streets/Roads |
-19 |
| Laramie Avenue Reconstruction |
Alsip |
IL |
16 |
$600,000 |
Streets/Roads |
-16 |
| Village wide sidewalk replacement program |
Alsip |
IL |
14 |
$425,000 |
Streets/Roads |
-32 |
| Sanitary Cured-in-Place Sewer Lining |
Alsip |
IL |
26 |
$1,000,000 |
Water |
-7 |
| Pump Station and Reservoir Expansion |
Alsip |
IL |
21 |
$800,000 |
Water |
2 |
| COPS Universal Hiring Program |
Alsip |
IL |
3 |
$225,000 |
Public Safety |
-52 |
| The widening of Fosterburg Rd. from IL Route 255 south to IL Route 140. Project includes the expansion of lanes from 10' to 12' plus the addition of a bi-directional turn lane. Additional improvements include patching and repaving of existing surfaces, |
Alton |
IL |
100 |
$4,245,940 |
Streets/Roads |
5 |
| Construction of a 278' extension of Morrison Avenue from Cpl. Belchik Memorial Expressway (formerly Indiana Ave.) to Alton Steel Industrial Park. The roadway improvements would accommodate and improve access for industrial and commercial transport. |
Alton |
IL |
100 |
$240,000 |
Streets/Roads |
11 |
| The City of Alton seeks funding to complete an urban redevelopment project located within a blighted area of Alton's central business district. The three (3) block project area suffers from a host of environmental remediation and flood plain issues after |
Alton |
IL |
200 |
$2,000,000 |
CDBG |
18 |
| Expansion of the downtown streetscape improvement project to compliment development projects currently under construction, including the Madison County Transit transfer station and the Landmarks Boulevard Pedestrian Overpass. Project improvements include |
Alton |
IL |
100 |
$750,000 |
CDBG |
28 |
| Complete reconstruction of the entire Division Street section, between Prospect Street and East Main Street, while reconstructing all of the utilities and making drainage improvements. |
Amboy |
IL |
95 |
$3,400,000 |
CDBG |
-21 |
| Complete reconstruction of the entire East Main Street section while reconstructing all of the utilities and making drainage improvements. |
Amboy |
IL |
70 |
$2,500,000 |
CDBG |
-10 |
| Providing a park at the North end of the City, with a playground, sand volleyball court, green space, and a pool. Along with this is a detention facility to prevent flooding downstream. |
Amboy |
IL |
64 |
$2,300,000 |
CDBG |
-97 |
| Complete reconstruction of the entire Provost Street section in front of Central School, while reconstructing all the utilities and making drainage improvements. |
Amboy |
IL |
28 |
$1,000,000 |
CDBG |
1 |
| Construction of an additional maintenance building that would allow for more storage space and maintenance on equipment. |
Amboy |
IL |
7 |
$250,000 |
CDBG |
-38 |
| Street Rehabilitation |
Arlington Heights |
IL |
25 |
$20,000,000 |
Streets/Roads |
-82 |
| Street Resurfacing |
Arlington Heights |
IL |
20 |
$15,000,000 |
Streets/Roads |
-50 |
| Water & Sewer Intrastructure Rehabilitation |
Arlington Heights |
IL |
20 |
$10,000,000 |
Water |
-14 |
| Sanitary Lift Station Elimination |
Arlington Heights |
IL |
10 |
$2,000,000 |
Water |
-16 |
| Street Rehabilitation |
Arlington Heights |
IL |
25 |
$2,000,000 |
CDBG |
-17 |
| Street Resurfacing |
Arlington Heights |
IL |
20 |
$1,500,000 |
CDBG |
-17 |
| Renewable Energy; solar power for downtown train station |
Arlington Heights |
IL |
0 |
$1,500 |
Energy |
-7 |
| Overlay of existing streets |
Aurora |
IL |
82 |
$4,000,000 |
Streets/Roads |
6 |
| Traffic Signal Installation at 4 congested intersections |
Aurora |
IL |
24 |
$450,000 |
Streets/Roads |
-14 |
| Combined Sewer Overflow / Sewer Separation Project - Basin 13 - Phase 3 |
Aurora |
IL |
68 |
$3,000,000 |
Water |
9 |
| Combined Sewer Overflow / Sewer Separation Project - Basin 6 |
Aurora |
IL |
56 |
$2,200,000 |
Water |
6 |
| Water Main replacement projects on 5 roadways |
Aurora |
IL |
45 |
$1,910,000 |
Water |
2 |
| Combined Sewer Overflow / Sewer Separation Project - Basin 13 - Phase 2 |
Aurora |
IL |
30 |
$600,000 |
Water |
10 |
| Airport Runway 18/36 Reconstruction |
Aurora |
IL |
76 |
$3,000,000 |
Airport |
70 |
| Construction of Station Blvd from Liberty Street to the Metra Commuter Station to improve traffic flow and allow the Commuter Parking lot to be reconfigured to add additional spaces. |
Aurora |
IL |
107 |
$7,500,000 |
Transit |
21 |
| Well #8 Barium and Radium Removal System - This project consists of a new treatment system to remove barium and radium from Well #8. This well draws from the same water aquifer as Well #4 (Stearns Road Booster Station) and Well #7 (Kent Circle Water Stat |
Bartlett |
IL |
12 |
$480,000 |
Water |
28 |
| Influent Pump Replacement - This project consists of replacing the three influent pumps and control system at the Stearns Road Wastewater Treatment Plant. The pumps were installed in 1975. Since that time the pumps and drive system have become obsolete. |
Bartlett |
IL |
6 |
$315,000 |
Water |
19 |
| Stearns Rd. Iron Filter Tank Replacement - The project consists of replacing the tank for the existing iron removal filter. The existing tank is over 20 years old and has significant corrosion. |
Bartlett |
IL |
9 |
$275,000 |
Water |
12 |
| Route 25 Road Improvements - These road improvements will provide access to the Blue Heron Business Park and the Bluff City Industrial Park. |
Bartlett |
IL |
50 |
$2,499,000 |
CDBG |
-27 |
| Schick Rd. Bridge Repairs - Repairing the Schick Road Bridge substructure and abutments as well as the east and west approach pavements. |
Bartlett |
IL |
25 |
$430,000 |
CDBG |
20 |
| West Bartlett and Naperville Roads Bike Path - This project consists of installing a 10 foot wide bike path within the existing West Bartlett Road and Naperville Road rights-of-way from the intersection of West Bartlett Road/Park Place Drive |
Bartlett |
IL |
12 |
$276,000 |
CDBG |
-41 |
| Bridge Rehabilition Chatham Street Bridge Over Calumet Sag Channel |
Blue Island |
IL |
217 |
$6,500,000 |
Streets/Roads |
36 |
| Bridge Rehabilitation Division Street Bridge Over Calumet Sag Channel |
Blue Island |
IL |
217 |
$6,500,000 |
Streets/Roads |
46 |
| Resurfacing 120th Pl, 121st St, 122nd St, Grunewald, Orchard, Highland, Maple, Ann |
Blue Island |
IL |
87 |
$2,600,000 |
Streets/Roads |
26 |
| Street Lighting |
Blue Island |
IL |
83 |
$2,500,000 |
Streets/Roads |
18 |
| Resurfacing Canal, Rexford, Gregory, Irving, Chicago, Hoyne, Seeley |
Blue Island |
IL |
80 |
$2,400,000 |
Streets/Roads |
9 |
| Resurfacing Minnesota, Edison, Everett, Wahl, Francisco, California |
Blue Island |
IL |
74 |
$2,200,000 |
Streets/Roads |
8 |
| Resurfacing Union, High, York, New |
Blue Island |
IL |
65 |
$1,900,000 |
Streets/Roads |
23 |
| Resurfacing Grunewald, Orchard, Greenwood, Artesian |
Blue Island |
IL |
57 |
$1,900,000 |
Streets/Roads |
13 |
| Resurfacing 119th Pl, 120th St, 120th Pl, 121st St. Longwood |
Blue Island |
IL |
64 |
$1,900,000 |
Streets/Roads |
17 |
| Resurfacing Collins, Cochran, Lewis, Birdsall, Greenwood |
Blue Island |
IL |
60 |
$1,800,000 |
Streets/Roads |
15 |
| Resurfacing 119th Pl, 120th St, 120th Pl, Gregory |
Blue Island |
IL |
60 |
$1,750,000 |
Streets/Roads |
9 |
| Reconstruction of 119th Street and Division Street |
Blue Island |
IL |
52 |
$1,700,000 |
Streets/Roads |
8 |
| Resurfacing Curb Removal and Replacement |
Blue Island |
IL |
50 |
$1,500,000 |
Streets/Roads |
10 |
| Resurfacing 123rd Pl, Krueger, Orchard, Collins |
Blue Island |
IL |
43 |
$1,500,000 |
Streets/Roads |
6 |
| Resurfacing Handicap Ramps and Sidewalk Replacement |
Blue Island |
IL |
49 |
$1,450,000 |
Streets/Roads |
3 |
| Resurfacing 135th St, Mozart, California, Vine |
Blue Island |
IL |
44 |
$1,350,000 |
Streets/Roads |
0 |
| Resurfacing Grove, Chatham |
Blue Island |
IL |
39 |
$1,300,000 |
Streets/Roads |
5 |
| Resurfacing Groove, Ann, James |
Blue Island |
IL |
44 |
$1,300,000 |
Streets/Roads |
5 |
| Resurfacing 135th St, 136th St |
Blue Island |
IL |
35 |
$1,200,000 |
Streets/Roads |
4 |
| Relining Combination Sewers |
Blue Island |
IL |
60 |
$1,750,000 |
Water |
12 |
| Manhole Lining |
Blue Island |
IL |
50 |
$1,500,000 |
Water |
-5 |
| Repainting 1,000,000 Gallon Elevated Tank (Highland Avenue) |
Blue Island |
IL |
35 |
$900,000 |
Water |
-7 |
| Water valve removal and replacement |
Blue Island |
IL |
30 |
$875,000 |
Water |
15 |
| Fire Hydrant Removal and Replacement |
Blue Island |
IL |
30 |
$840,000 |
Water |
17 |
| Repainting 1,000,000 Gallon Elevated Tank (Thorton-Blue Island Road) |
Blue Island |
IL |
25 |
$750,000 |
Water |
-16 |
| Full interchange at I-55 and Il. Rt. 126 |
Bolingbrook |
IL |
0 |
$12,000,000 |
Streets/Roads |
24 |
| Kings Road, Hassert to Rodeo: construct urban cross-section roadway with landscaped median and bridge over the Lily Cache Creek. |
Bolingbrook |
IL |
70 |
$6,800,000 |
Streets/Roads |
-9 |
| Lily Cache Lane, Route 53 to Schmidt Road: reconstruct 2 lane roadway to 4 lanes plus a landscaped median. |
Bolingbrook |
IL |
70 |
$5,900,000 |
Streets/Roads |
-3 |
| Boughton Road rehabilitation, Pinecrest to Schmidt: repair curbs and stormsewers then patch and pave roadway. |
Bolingbrook |
IL |
23 |
$3,000,000 |
Streets/Roads |
2 |
| Road rehabilitation program: perform pavement maintenance activities up to and including paving on a number of streets that have not been paved in over 20 years. |
Bolingbrook |
IL |
30 |
$2,000,000 |
Streets/Roads |
12 |
| Lindsey Lane, Lily Cache Lane to existing Lindsey Lane stub: construct new roadway to provide access to Jane Addams School (school district project, with recapture from future developers). |
Bolingbrook |
IL |
58 |
$1,000,000 |
Streets/Roads |
-9 |
| Reagan Boulevard from Danhoff Lane to Plainfield-Naperville Road: reconstruction of a two lane country roadway to a urban cross-section with center median. |
Bolingbrook |
IL |
58 |
$900,000 |
Streets/Roads |
-10 |
| Traffic signal at St. James and Joliet Road, and roadway improvements to the north leg of intersection. |
Bolingbrook |
IL |
58 |
$800,000 |
Streets/Roads |
0 |
| St. Andrew's Drive extension: extend St. Andrew's Drive and connect to quarry driveway. |
Bolingbrook |
IL |
48 |
$700,000 |
Streets/Roads |
-6 |
| Kings Road landscaped median: construct landscaped median to calm traffic, reduce runoff, and beautify the roadway. |
Bolingbrook |
IL |
15 |
$400,000 |
Streets/Roads |
-16 |
| Weber Road landscaped medians, north and south of Jennifer Lane. |
Bolingbrook |
IL |
15 |
$400,000 |
Streets/Roads |
-38 |
| Traffic signal on Remington Boulevard and Schmidt Road, plus interconnect to traffic signal at hospital entrance. |
Bolingbrook |
IL |
5 |
$300,000 |
Streets/Roads |
-4 |
| Traffic signal at entrance to Gateway East and Costco site. |
Bolingbrook |
IL |
5 |
$300,000 |
Streets/Roads |
-10 |
| Frontage Road removal: remove abandoned frontage road and replace with topsoil and turf from Weber Road to Remington Boulevard. |
Bolingbrook |
IL |
10 |
$300,000 |
Streets/Roads |
-17 |
| Traffic signal on Remington Boulevard at entrance to Adventist Bolingbrook Hospital. |
Bolingbrook |
IL |
5 |
$300,000 |
Streets/Roads |
-3 |
| Traffic signal on Hassert Boulevard and Kings Road. |
Bolingbrook |
IL |
5 |
$300,000 |
Streets/Roads |
-1 |
| Route 53 entrances to Arena Auto Auction: remove obsolete entrances / turn bays built for former Old Chicago amusement park. |
Bolingbrook |
IL |
11 |
$100,000 |
Streets/Roads |
-19 |
| Clow Airport traffic Circle: install a traffic circle on Clow Parkway to safely guide traffic into the airport. |
Bolingbrook |
IL |
10 |
$100,000 |
Streets/Roads |
-17 |
| Sewer plant expansion at Indian Boundary treatment plant |
Bolingbrook |
IL |
0 |
$10,000,000 |
Water |
0 |
| Clow Airport, runway improvements: widen existing runway to allow use by larger planes. |
Bolingbrook |
IL |
22 |
$10,000,000 |
Airport |
-47 |
| New Runway at Bolingbrook-Clow Airport |
Bolingbrook |
IL |
0 |
$10,000,000 |
Airport |
-41 |
| Clow Airport: add additional hangers. |
Bolingbrook |
IL |
50 |
$4,000,000 |
Airport |
-39 |
| Police Department expansion: construction of an addition to the curent Police Department facility. |
Bolingbrook |
IL |
95 |
$10,000,000 |
CDBG |
-60 |
| Kings Road Extension |
Bolingbrook |
IL |
0 |
$10,000,000 |
CDBG |
-5 |
| Lily Cach Lane Widdening |
Bolingbrook |
IL |
0 |
$4,000,000 |
CDBG |
-10 |
| Cumberland Pond: dredging and rehabilitation of pond to improve water quality, fish habitat, and aestetics. |
Bolingbrook |
IL |
24 |
$700,000 |
CDBG |
-26 |
| Briarcliff Road stormsewer: replace a few hundred feet of stormsewer on Briarcliff Road as part of the master plan to resolve flooding problems in Historic Bolingbrook. |
Bolingbrook |
IL |
18 |
$500,000 |
CDBG |
7 |
| Barbers Corners water & sewer: installation of water and sewer lines to remove several houses from well and septic systems. |
Bolingbrook |
IL |
15 |
$400,000 |
CDBG |
0 |
| Boughton Road sidewalk: construct sidewalk and related work to fill in missing gap in sidewalk network on Boughton Road by the Independent Baptist Church. |
Bolingbrook |
IL |
14 |
$200,000 |
CDBG |
-1 |
| Historic Bolingbrook sidewalk construction: phase 11 includes constructing sidewalks in neighborhoods that do not have them on four streets. |
Bolingbrook |
IL |
10 |
$200,000 |
CDBG |
-23 |
| River Woods erosion control, phase 2: installation of gabion baskets, rip-rap, and other non-stuctural measures to restore the highly eroded banks of the creek in the River Woods neighborhood. |
Bolingbrook |
IL |
10 |
$200,000 |
CDBG |
4 |
| Public Works Garage, add heavy duty shelving: add shelving to enable safe and cost effective storage of emergency supplies, supplies bought in bulk, and other necessary items. |
Bolingbrook |
IL |
5 |
$100,000 |
CDBG |
-41 |
| I-55 full interchange at Rt. 126 |
Bolingbrook |
IL |
0 |
$12,000,000 |
Transit |
-19 |